BLID - Phase 1 Notices
It took us so long to get the Broadway LID construction bid approved, that we almost forgot it involves real work getting done too. A notice began appearing on cars yesterday that announced the first phase of the project to those that park on the affected streets. The gist of it comes down to:
… All parking on Broadway between South 7th and South 2nd will be temporarily eliminated. Soon, you will see large signs installed with the actual start date, but we wanted to notify you early so you can find alternate parking.
Here’s the rest of the construction schedule.
Phase 1
Broadway
South 6th – South 2nd & South 4th
June 2008
Phase 2
Market Street
South 9th – South 7th
October 2008
Phase 3
Broadway
South 9th – South 6th & South 7th
April 2009
Phase 4
St. Helens
South 9th – South 7th
July 2009
The Broadway LID is scheduled to be complete in the summer of 2009.
More information, background, and a public meeting schedule can be found at www.cityoftacoma.org/BroadwayLID
Filed under: Developments
1 comments
E Erik B. May 29, 2008
Yep. Saw those on the cars all along Broadway. Hang on.