Many I-5 lane and ramp closures occur in Tacoma

Drivers traveling on Interstate 5 through Tacoma will encounter lane and ramp closures for I-5 construction.
The closures are scheduled as follows:
9 p.m. Monday and Tuesday, Sept. 15-16
• Closing single right lane of northbound I-5 from milepost 132.4 to 135.2.
• Lane will reopen by 5 a.m. each following morning.
Wednesday, Sept. 17
• 8 p.m. - closing single southbound right lane near M Street;
• 9 p.m. - closing single northbound lane near McKinley Street, and also at M Street (two separate lane closures).
• 10 p.m. - closing several facilities:
o second southbound right lane
o southbound I-5 exit to northbound Interstate 705 and to southbound State Route 7
o Portland Avenue on-ramp to southbound I-5
o State Route 167 on-ramp to southbound I-5
• All lanes and ramps will reopen by 6 a.m. Thursday.
Thursday, Sept. 18
• 9 p.m. – closing southbound I-5 single left lane near M Street
• 11 p.m. – closing second southbound I-5 left lane
• All lanes will reopen by 6 a.m. Friday.
Friday, Sept. 19
• 10 p.m. – closing southbound I-5 single left lane near M Street
• midnight – closing second southbound I-5 left lane
• All lanes will reopen by 6 a.m. Saturday
This work is part of the I-5: M Street to Portland Avenue – HOV project.